Template · Bidding
Subcontractor bid leveling sheet
Level subcontractor bids for scope gaps: each excluded or qualified item adds its plug value to the base bid.
Downloads are included in the $19.85 yearly membership. Sign in
XLSXCSVODSXMLNumbers| Subcontractor bid leveling | |||||||||
| Example data — replace the blue input cells with your own. | |||||||||
| LOWEST LEVELED SUB | LEVELED AMOUNT | LOWEST BASE BID | LEVELED LESS LOWEST BASE BID | ||||||
| Example Mechanical Co. | $1,934,400 | Riverbend Example Mechanical | $50,400 | ||||||
| Trade | Mechanical (HVAC) | ||||||||
| Project | Example Elementary School addition | ||||||||
| Qualified item adjustment (share of plug value) | 50% | A qualified item adds this share of its plug value to the base bid | |||||||
| Subcontractors | |||||||||
| Subcontractor | Example Mechanical Co. | Northwind Example HVAC | Riverbend Example Mechanical | Hillcrest Example Inc. | |||||
| Base bid (as submitted) | $1,912,000 | $1,968,500 | $1,884,000 | $1,936,250 | |||||
| Scope status by subcontractor (Included, Excluded or Qualified) | |||||||||
| Scope item | Plug value | Example Mechanical Co. | Northwind Example HVAC | Riverbend Example Mechanical | Hillcrest Example Inc. | Adjustment: Example Mechanical Co. | Adjustment: Northwind Example HVAC | Adjustment: Riverbend Example Mechanical | Adjustment: Hillcrest Example Inc. |
| Ductwork fabrication and installation | $42,000 | Included | Included | Excluded | Included | $0 | $0 | $42,000 | $0 |
| Duct insulation | $9,500 | Included | Included | Excluded | Included | $0 | $0 | $9,500 | $0 |
Showing the first 16 of 49 rows and 10 of 10 columns. Cells with formulas show the formula on hover.
| Scope checklist and plug values | |||
| One trade. Each scope item has a plug value: the estimated cost the GC carries if a sub excludes that item. | |||
| Scope items for the trade on the Leveling tab | |||
| # | Scope item | Plug value | What the plug covers |
| 1 | Ductwork fabrication and installation | $42,000 | Labor, material and hangers for the duct runs in the bid documents |
| 2 | Duct insulation | $9,500 | Insulation to the specified R-value, including jacketing |
| 3 | Air terminal devices (diffusers and grilles) | $6,800 | Diffusers, grilles and registers scheduled on the drawings |
| 4 | Rooftop unit setting | $11,500 | Rigging and setting of each rooftop unit |
| 5 | Crane and rigging | $14,000 | Crane time, operator and rigging for equipment lifts |
| 6 | Refrigerant piping | $8,200 | Piping and specialties from the condenser to the evaporator |
| 7 | Condensate drainage | $2,400 | Traps, drain lines and tie-ins to the building drain |
| 8 | Exhaust fans | $3,900 | Fans, curbs and disconnects for exhaust |
| 9 | Thermostats and control wiring | $5,600 | Thermostats, sensors and low-voltage wiring |
| 10 | Building automation controls and programming | $12,800 | Controls panels, points list and programming |
| 11 | Test and balance | $9,200 | Air and water balancing, with a written report |
Showing the first 16 of 24 rows and 4 of 4 columns. Cells with formulas show the formula on hover.
| Subcontractor bid leveling |
| Notes: what this workbook does, how to use it and the method behind it. |
| What it does |
| Puts subcontractor bids for one trade on the same scope. Each bid is adjusted for the scope items it excludes or qualifies, so the leveled bids can be compared. The example is a mechanical (HVAC) package for four subcontractors. |
| How to use it |
| 1. Enter the trade and project on the Leveling tab. |
| 2. On the Scope tab, list the scope items for the trade and enter a plug value for each: the estimated cost of the item if a sub excludes it. |
| 3. Enter each subcontractor's name and base bid in the Subcontractor and Base bid rows. |
| 4. For each scope item and subcontractor, choose Included, Excluded or Qualified. Blank or misspelled entries are reported as invalid. |
| 5. Read the lowest leveled sub, the leveled amount and the leveled bid less the lowest base bid in the Summary tiles, then review each sub's exclusions. |
| Formulas and method |
| Adjustment per item: Excluded adds the plug value; Qualified adds the plug value times the qualified factor; Included adds nothing. |
| Total adjustments: sum of the item adjustments for each subcontractor. |
Showing the first 16 of 31 rows and 1 of 1 columns. Cells with formulas show the formula on hover.
What does this template do?
Subcontractor bids for the same trade rarely cover the same scope. One sub excludes controls, another qualifies its crane time, and the lowest base bid may be the one that leaves the most out. A general contractor uses a leveling sheet to put the bids on one basis before choosing a sub. This workbook is set up for one trade, mechanical (HVAC) in the example, and four subcontractors.
The Scope tab lists the scope items with a plug value for each, which is the estimated cost to carry the item if a sub excludes it. On the Leveling tab, each sub's status for each item is Included, Excluded or Qualified. An Excluded item adds its full plug value to the base bid, a Qualified item adds the plug value times a qualified factor, and an Included item adds nothing. The leveled bid is the base bid plus the total of those adjustments, and the leveled bids are ranked.
All names, bid amounts, plug values and statuses are fictional example data. The plug values are estimates, not market quotes.
What’s inside
- Scope checklist of 18 items for one trade, each with a plug value
- Included, Excluded and Qualified status for each item and each of four subcontractors
- Adjustments and leveled bid for each subcontractor, ranked lowest first
- Gap to the lowest leveled bid and the lowest base bid shown in the summary tiles
- Check for statuses that are blank or misspelled
Which tabs does the workbook have?
| Tab | What it holds |
|---|---|
| Leveling | Trade and project inputs, subcontractor base bids, scope statuses, adjustments and the leveled summary. |
| Scope | Scope items for the trade, the plug value for each and what the plug covers. |
| Notes | Purpose, steps, formulas used, assumptions and limits. |
What formulas does this template use?
This template holds 168 formulas in 385 cells across 3 tabs, so 44% of its cells calculate. They use 10 distinct functions; the longest formula is 204 characters and 36 of them read from another tab.
| Function | Uses | What it does |
|---|---|---|
IF | 272 | one result when a test is true, another when false |
COUNTIF | 20 | counts cells meeting one condition |
SUM | 9 | adds numbers |
MIN | 8 | smallest value |
RANK | 8 | position of a value in a list |
COUNT | 7 | counts numeric cells |
COUNTA | 4 | counts non-empty cells |
INDEX | 2 | value at a position in a range |
MATCH | 2 | position of a value in a range |
OR | 1 | true when any test is true |
Counted from the workbook itself. Only functions that Excel, LibreOffice Calc, Google Sheets and Apple Numbers evaluate the same way are used, so the formulas survive every download format.
How do you use it?
- On the Scope tab, list the scope items for the trade and enter a plug value for each.
- On the Leveling tab, enter the trade, the project and the qualified factor.
- Enter each subcontractor's name and base bid.
- For each scope item and subcontractor, choose Included, Excluded or Qualified.
- Read the lowest leveled sub and the leveled amount, then review the exclusions and qualifications for each sub.
What is it good for?
- Comparing mechanical, electrical or plumbing sub bids before award
- Showing a sub how its exclusions change its position
- Recording which scope items each sub carries in the bid
Questions about this sheet
What is a plug value?
A plug value is the estimated cost to carry a scope item when a subcontractor leaves it out. It is set by the general contractor, and it is added to the base bid when the item is excluded.
How is a qualified item priced?
A qualified item adds the plug value times the qualified factor, which is 50% in the example. Change the factor on the Leveling tab to match how you price qualifications.
Why does the lowest leveled sub differ from the lowest base bid?
The leveled bid adds the cost of excluded and qualified items to the base bid. A sub with a low base bid and many exclusions can rank below a sub with a higher base bid and full scope.