Template · Bidding

Unit price bid schedule with alternates

Base bid by section, with allowances, contingency, add and deduct alternates and a total contract amount.

Create an account

Downloads are included in the $19.85 yearly membership. Sign in

XLSXCSVODSXMLNumbers
Unit price bid summary
Example data — replace the blue input cells with your own.
BASE BIDACCEPTED ALTERNATES, NETTOTAL CONTRACT AMOUNT
$697,583$2,500$700,083
Base bid by section
SectionAmountShare of base bidLines with an amount
General$55,9008.0%3
Earthwork$101,64514.6%3
Paving$337,56048.4%5
Utilities$96,23013.8%5
Landscaping$40,0305.7%5
Allowances$33,0004.7%2
Contingency$33,2184.8%1
Base bid total$697,583100.0%24

Showing the first 16 of 28 rows and 4 of 4 columns. Cells with formulas show the formula on hover.

What does this template do?

A unit price bid schedule is the form a contractor completes for a public or private site project. Each item has a fixed quantity from the bid documents and a unit price that the contractor enters. This workbook extends each line, adds the owner's allowances and a contingency, and totals the base bid by section. Add and deduct alternates are priced separately, and each one moves the total contract amount only when it is accepted.

The Base bid tab holds up to 100 item rows in five sections: General, Earthwork, Paving, Utilities and Landscaping. The Summary tab sums each section with SUMIF, shows each section's share of the base bid, and counts quantity lines with no unit price. The Alternates tab takes each alternate's type, positive amount and accepted status, and signs the accepted amounts. The contract amount is the base bid plus the net effect of the accepted alternates.

The project, quantities, unit prices, allowances and alternates are fictional. Example Park site improvements is a made-up project, and the figures are for layout only.

What’s inside

  • Extended amounts for up to 100 items, grouped in five sections
  • Owner allowances and a percentage contingency below the items
  • Section subtotals with SUMIF and each section's share of the base bid
  • Five add and deduct alternates, signed only when accepted
  • Check for quantity lines without a unit price

Which tabs does the workbook have?

TabWhat it holds
SummaryBase bid, accepted alternates and total contract amount, section subtotals, alternates summary and checks.
Base bidItems with quantity, unit price and extended amount, followed by allowances, contingency and the base bid total.
AlternatesAdd and deduct alternates with amount, accepted status and signed amount.
NotesPurpose, steps, formulas used, assumptions and limits.

What formulas does this template use?

This template holds 148 formulas in 383 cells across 4 tabs, so 39% of its cells calculate. They use 9 distinct functions; the longest formula is 207 characters and 21 of them read from another tab.

FunctionUsesWhat it does
IF152one result when a test is true, another when false
OR110true when any test is true
SUMPRODUCT9multiplies matching entries, then adds them
ISNUMBER7true for a number
SUM7adds numbers
SUMIF7adds values meeting one condition
SUMIFS2adds values meeting several conditions
ABS1absolute value
COUNTIF1counts cells meeting one condition

Counted from the workbook itself. Only functions that Excel, LibreOffice Calc, Google Sheets and Apple Numbers evaluate the same way are used, so the formulas survive every download format.

How do you use it?

  1. On the Base bid tab, enter each item's section, item number, description, unit and quantity from the bid documents.
  2. Enter the unit price for each item in the blue column.
  3. Enter the allowance amounts and the contingency percentage.
  4. On the Alternates tab, enter each alternate with its type, positive amount and accepted status.
  5. Read the base bid, the accepted alternates and the total contract amount on the Summary tab.

What is it good for?

  • Pricing a unit price bid for site improvements
  • Showing the effect of accepted add and deduct alternates on the contract
  • Checking that every quantity line has a unit price before submitting the bid

Questions about this sheet

How is contingency calculated?

Contingency is the contingency percentage times the sum of the item amounts and the allowances. It is calculated after the allowances, so changing an allowance also changes the contingency.

What happens if an item has no unit price?

Its extended amount stays blank, so the base bid leaves it out. The Summary tab reports how many quantity lines have no unit price.

Are deducts shown as negative amounts?

Yes. Enter the deduct amount as a positive number and set its type to Deduct. An accepted deduct is shown as a negative amount, and only accepted alternates change the total.