Assembly line balancing calculator with takt time

Takt time, station loading, line efficiency and balance delay for a task list with precedence.

Create an account

Downloads are included in the $19.85 yearly membership. Sign in

XLSXCSVODSXMLNumbers
Assembly line balancing with takt time
Example data — replace the blue input cells with your own.
Blue cells are inputs. Takt = net available seconds per day / demand per day.
TAKT TIME (S PER UNIT)MINIMUM STATIONSSTATIONS USEDLINE EFFICIENCY
45.04490.9%
Takt timeLine balance
Available time per shift (min)480Total work content (s)160
Breaks per shift (min)30Theoretical minimum stations4
Shifts per day2Stations used4
Demand per day (units)1,200Longest station time (s)44.0
Net available time per day (min)900Line efficiency90.9%
Takt time (s per unit)45.0Balance delay9.1%
Precedence and takt checksOK: no precedence or takt problems
Task table (60 rows; one row per task)
Task IDDescriptionTask time (s)Predecessor 1Predecessor 2StationStation of predecessor 1Station of predecessor 2Precedence checkCumulative station time (s)Cumulative check

Showing the first 16 of 77 rows and 11 of 11 columns. Cells with formulas show the formula on hover.

What does this template do?

Line balancing shares an assembly task list across workstations so that every station finishes its work within the takt time. This workbook is for industrial engineers and line supervisors who lay out an assembly line or test a new task assignment.

Takt time is net available time per day divided by daily demand, in seconds per unit. Each task has a time, up to two predecessors and a station number. The Line tab looks up the station of each predecessor and flags any task that sits before a predecessor. A running total of station time is compared with takt for each task.

The Stations tab adds up task times for each station, shows idle time and utilization, and marks stations over takt. Line efficiency is total work content divided by stations used times the longest station time, and balance delay is one minus efficiency. The example data is fictional: fourteen tasks for a small appliance.

What’s inside

  • Takt time from available time, breaks, shifts and daily demand
  • Predecessor stations checked against each task's station
  • Running station time checked against takt for every task
  • Station loading for up to 15 stations, with idle time and utilization
  • Line efficiency and balance delay from total work content and the longest station

Which tabs does the workbook have?

TabWhat it holds
LineTakt inputs, the balance summary and the task table with precedence and cumulative checks.
StationsStation time, idle time, utilization and status for stations 1 to 15.
NotesWhat the workbook does, the formulas in words, assumptions and limits.

What formulas does this template use?

This template holds 396 formulas in 562 cells across 3 tabs, so 70% of its cells calculate. They use 15 distinct functions; the longest formula is 232 characters and 34 of them read from another tab.

FunctionUsesWhat it does
IF863one result when a test is true, another when false
INDEX240value at a position in a range
MATCH240position of a value in a range
OR180true when any test is true
AND121true when every test is true
IFERROR120swaps an error for a fallback value
ISNUMBER120true for a number
SUMIF75adds values meeting one condition
COUNTIF19counts cells meeting one condition
SUM5adds numbers
COUNT2counts numeric cells
COUNTA1counts non-empty cells

The 12 most used of 15 functions. Counted from the workbook itself. Only functions that Excel, LibreOffice Calc, Google Sheets and Apple Numbers evaluate the same way are used, so the formulas survive every download format.

How do you use it?

  1. Enter available time, breaks, shifts per day and daily demand on the Line tab to get takt time.
  2. Type each task with its time in seconds and up to two predecessor task IDs.
  3. Assign each task to a station number in the blue Station column.
  4. Read the Precedence check and Cumulative check columns, and fix any task marked with a flag.
  5. Read line efficiency, balance delay and station status on the Line and Stations tabs.

What is it good for?

  • Balancing a small appliance assembly line
  • Checking whether a proposed station layout meets takt
  • Estimating the stations needed for a new demand level
  • Comparing two task assignments before a layout change

Questions about this sheet

What is takt time?

Takt time is the available working time divided by customer demand, so it is the pace a line must keep to meet demand. The sheet gives it in seconds per unit.

What does the precedence check test?

It tests whether each task's predecessors sit at its own station or at an earlier one. A task whose predecessor sits at a later station is flagged as Precedes a later station.

How is line efficiency calculated?

Line efficiency is total task time divided by the number of stations used multiplied by the longest station time. Balance delay is one minus that efficiency.

Does the workbook search for a better station assignment?

No. It checks the assignment you enter against takt and precedence, and it does not search for a better one.